Project Portfolio

Nexteer Automotive – World Headquarters
Project Team: 
CB Richard Ellis – Scott Cave 248.914.3184
Landry / Cekauskas Architecture – Raymond Cekauskas 248.593.6577
D&S Project Manager – Lewis Maynard 248.584.4848

Project Scope: 54,200 sf, Open Office with Open R&D Space

Cost:

$3,670,000

Duration: 180 days

Architect: Raymond Cekauskas

Relevant Highlights: 

Fast Track Project
Finish space relocated their Global Headquarters